Key Highlights:
- Project County: Wayne
- Project Summary: Civil Engineering plans were prepared for rehabilitation and replacement of the pavement in the parking areas and roadway. The total cost of this project is $515,000.00 and the design cost is $42,000.00.

Hammontree was hired by The Ohio State University to redesign the entrance of their Wooster Campus to accommodate truck traffic and improve the general traffic flow. Civil Engineering plans were prepared for rehabilitation and replacement of the pavement in the parking areas and roadway. The total cost of this project is $515,000.00 and the design cost is $42,000.00.
Services:
- Base Topographic Survey and Mapping
- Pavement Analysis
- Redesign of Drives and Parking
- Civil Site Engineering
- Construction Administration and Observation